Third quarter report 2025Cloudberry Clean Energy ASA
Operational review
Cloudberry is structured into three collaborative segments: Projects, Commercial, and Asset Management, enabling efficient management and optimization of Cloudberry’s renewable energy assets across the Nordics while enabling growth across all core areas.
Projects: Focuses on greenfield development, permitting, procurement, and construction.
Commercial: Increases and optimizes the portfolio, M&A, boosts EBITDA for the Group, reduces risk and incorporates new hybrid solutions into Cloudberry’s projects.
Asset Management: Concentrates on the efficient day-to-day operations of both internal and external hydro, wind, and solar projects in the Nordics.
Where to play – proven and uncorrelated technologies
Cloudberry focuses on proven and uncorrelated technologies across the Nordic countries. The following table details the strategic focus areas with the dark blue indicating key focus areas.
Projects
Projects under construction
Forte construction projects (Hydro): Through Cloudberry’s newly established 60% ownership in Forte Vannkraft, which closed at the beginning of the quarter, Cloudberry is actively involved in the development of several small-scale hydro projects currently under construction. These projects, detailed in the portfolio overview, have a combined estimated annual production net to Cloudberry of approximately 81 GWh, with expected completion dates spanning from fourth quarter of 2025 to 2028. For further details, please refer to the portfolio overview and the Commercial segment for more information about the Forte transaction. The construction projects have been progressing as planned since close of the transaction.
Subsequent to the quarter, the Norwegian Government, through the Finance Ministry, presented a consultation proposal to lower threshold for the resource rent tax. This proposal is further explained in the Corporate segment reporting. In light of this the Kalklav project (9 GWh proportionate production in NO 4) is currently on hold and all the remaining hydro projects under construction are under review.
The total estimated remaining capital expenditure (capex) proportionate to Cloudberry for these projects is EUR 35 million, of which EUR 20 million relates to projects subject to resource rent tax under the current regime (not taking into account the new proposal further elaborated in the Corporate segment). As such, approximately EUR 11 million is expected to be reimbursed by the state through cash contributions linked to the current resource rent tax scheme, resulting in a net capex exposure for Cloudberry of EUR 24 million. This includes all the hydro projects under construction which are currently under review, including the paused project Kalklav with ~EUR 7m in remaining capex proportionate to Cloudberry.
Dingelsundet (Battery, SE-3). Hafslund and Cloudberry (50/50 owners) reached final investment decision (FID) in July 2025. The project is progressing well. Site preparations are well advanced, and the project remains on time and budget without any safety issues. Commissioning is expected in the third quarter of 2026.
The project will be financed with an equal split between equity and debt, making it one of the first BESS projects in the Nordics to secure project financing. The total estimated capex is approximately EUR 11 million on a 100% basis or EUR 5.5 million proportionate to Cloudberry. The project is a result of close collaboration between Hafslund and Cloudberry, with a successful shift from the offshore wind project Stenkalles to a battery energy storage project (BESS). The attractiveness of the BESS project has been made possible by, amongst other factors, a significant decline in battery costs in recent years and a strong market outlook for grid flexibility in the Karlstad region. The expected revenue streams from this industrial battery project will be uncorrelated with Cloudberry’s existing production, further strengthening the resilience and diversification of Cloudberry’s Nordic portfolio. The partners also see potential to expand the project with additional battery capacity, with site rights already secured.
As of the end of the third quarter 2025, the remaining capex for the Dingelsundet project proportionate to Cloudberry amounts to approximately EUR 4.5 million. The required equity to fully finance Dingelsundet was injected into the project at the beginning of the quarter reducing the consolidated cash position with the whole amount. As Dingelsundet is not consolidated in Cloudberry’s financial statements, the full equity injection is reflected as a cash outflow in the consolidated accounts, and the project is fully financed.
Producing projects with remaining construction activities
The two projects Sundby (Wind, SE-3) and Munkhyttan (Wind, SE-3) wind projects have both been successfully transferred to the Commercial segment at year end 2024. As of the end of the third quarter of 2025, the remaining capex amounts to approximately EUR 1.6 million for Sundby and EUR 0.3 million for Munkhyttan relating to final invoices. There has been a slight increase in the cost to finalize Sundby grid upgrade due to a change in the required grid route, however the project is still below the initial FID budgets. Please see previous quarterly reports relating to the pending grid upgrades for Sundby.
Projects with construction permit
Nees Hede (Solar, DK-1): The 232 MW Nees Hede solar project is fully permitted and strategically located in Jylland – Denmark, an area experiencing increasing industrial activity. In June, Sumitomo and our partner Skovgaard Energy announced a sustainable aviation fuel initiative. Further, datacentre activity in the region is accelerating, driven by a large-scale fiber connectivity hub in Esbjerg and new renewable energy projects to meet growing power demand.
Rather than taking an FID on the stand-alone solar project in 2025 with marginal economics, Cloudberry is prioritizing the development of a hybrid solution before FID. The targeted project will integrate battery storage, wind power and a bidirectional grid connection, significantly improving the project economics and positioning Cloudberry to attract new power-intensive industries seeking baseload production profiles and robust grid access. Applications for the wind turbines, BESS and bidirectional grid connection have been submitted and a minimum of 2.7 km² of land has been secured for 29 + 30 years. During the quarter the screening decision from Energinet was received, and Volder Mark substation will be connection point for the project. A maturation contract has been entered into with Energinet, and the process of defining the detailed specifications of the connection has started.
Duvhällen (Wind, SE-3):Cloudberry entered in the second quarter of 2025 into a partnership with OX2, divesting 60% of the Duvhällen project. Together, the partners plan to develop a hybrid solution that combines already permitted wind turbine positions with solar power and battery storage, enhancing supply reliability. Final investment decision (FID) is expected in 2026, with full operations targeted for 2028.
Backlog & pipeline
As of the reporting date, the backlog has increased to 1,357 MW across 45 exclusive projects, up from 1,033 MW in the same quarter last year.
The project backlog remains robust, with a continued focus on advancing permission processes, securing strong local anchoring, and fostering synergies with local industry. In the second quarter of 2025 Cloudberry entered into a partnership with Sveaskog, Europe’s largest forest owner, to jointly develop the Älgfallet renewable energy park (up to 300 GWh of wind, solar, and storage) in Nora municipality. This collaboration is the first time Sveaskog assumes an active ownership role in a development project, and as such marks the start of a long-term partnership with a shared ambition to explore similar opportunities. This cooperation further continued over the third quarter, and progressing according to plan.
As part of the Forte transaction, Cloudberry has contributed its hydro backlog to the Forte Vannkraft platform. Combined with Forte’s eight projects, the total hydro backlog now comprises 18 projects with an estimated ~165 GWh in proportionate annual production to Cloudberry. This new initiative, combined with Cloudberry’s existing hydro capabilities, features a strengthened development and construction team and establishes a solid foundation for attracting additional projects going forward.
Cloudberry is also working on a large non-exclusive pipeline of promising projects across Norway, Sweden, and Denmark, totaling above 2 500 MW of hydro, solar, and onshore wind projects.
Commercial
Commercial’s focus is to increase Cloudberry’s fundamental value by actively engaging in hydro, wind, solar and storage projects across the Nordic value chain.
Forte Transaction
In July, Cloudberry completed a transaction with Swiss Life Asset Managers to establish one of the largest small-scale hydro platforms in the Nordics, with Cloudberry as the controlling shareholder.
Through this transaction, Cloudberry contributed its entire hydropower portfolio and projects to Forte Vannkraft AS (FVK) at approximately 1.9x book values, resulting in a 60% ownership stake in FVK. The combined FVK platform now comprises 166 GWh of annual proportionate production to Cloudberry from operating and under-construction hydro assets, in addition to a substantial project backlog of 165 GWh proportionate to Cloudberry.
As part of the transaction, Cloudberry also acquired an additional 5.01% stake in the Forte Energy Norway (FEN) portfolio, increasing its total ownership to 55%. The FEN portfolio is now consolidated into Cloudberry’s accounts and consists of 14 hydropower plants and one power offtake agreement, with a total annual estimated production of 254 GWh on a 100% basis (139 GWh proportionate to Cloudberry).
Through the transaction Cloudberry also received an ownership of 45% in Norhard Equipment AS. Norhard is a construction company specializing in drilling for small scale hydro, enabling project realization and possibility to attract new hydro projects for FVK that require waterways through hard rock. Norhard will not be consolidated and the financials for Norhard in the proportionate reporting will be recorded in the Projects segment.
The FVK and the FEN portfolios will operationally be treated as one portfolio. Through this transaction, Cloudberry will increase its proportionate hydro production from ~200 GWh to ~300 GWh and the consolidated hydro portfolio will comprise around 500 GWh (73 GWh currently consolidated) of producing and under-construction hydropower plants. The majority of the combined portfolio is located in attractive southern price regions.
Please see the Financial Review for the accounting effects in the consolidated statements from this transaction.
The partnership with Swiss Life Asset Managers strengthens Cloudberry’s development capabilities with six FTE’s in FVK, expands its industrial network, and doubles its hydro asset management volumes. The combined portfolio is expected to deliver long-term cash flows, supported by an average asset life exceeding 50 years. Cloudberry will manage the portfolio and lead further development, with FVK operating as a dedicated platform for small-scale hydro in the Nordics.
Approximately 80% of FVK’s proportionate run‑rate production from assets in operation or under construction pre‑closing was already within the resource rent tax regime and is not impacted by the new tax proposal. Please refer to the Corporate segment reporting for further detail about the tax proposal.
Please see note 2 and the following press release for more information.
Power production
Cloudberry’s proportionate power production in the quarter totaled 177 GWh, a ~22% increase from 145 GWh in the same quarter last year. The table shows the proportionate production for the quarter, broken down by different price areas.
Production (GWh)
Q3 2025
Q3 2024
Q3 2025 LTM
FY 2024
NO-1
40
20
208
136
NO-2
22
24
80
77
NO-3
5
7
22
33
NO-4
-
-
-
3
NO-5
34
31
87
66
SE-3
24
14
135
90
DK-1
52
49
246
264
DK-2
1
1
6
6
Total
177
145
784
674
Of which hydro
58
60
177
171
Of which wind
119
85
607
503
Proportionate wind power production totaled 119 GWh over the quarter (85 GWh). The increase is primarily driven by ramp-up in production at Odal in NO-1 and completion of the Munkhyttan wind farm in SE-3. This was offset by lower production due to reduced wind speeds, especially evident in Denmark resulting only in a small production growth despite Cloudberry having increased its ownership from 80% to 100% in the first quarter of 2025. Lower wind speeds for the quarter also resulted in lower wind production in Sweden and Norway over the quarter.
Proportionate hydro power production totaled 58 GWh over the quarter (60 GWh). Please see the overview of the Forte transaction above, which represents the largest shift in the hydro power portfolio compared to the same quarter last year.
Odal Wind status update
As of the reporting date, all 34 turbines at Odal have met the return to service (RTS) criteria set by Siemens Gamesa and are fully operational. RTS status means the turbines are running but remain subject to a comprehensive inspection program. Production will continue to ramp up throughout 2025, as Odal undergoes this extended inspection process, which is expected to result in temporarily lower availability than normal.
Subsequent to quarter-end, Odal Wind declared a EUR 5 million dividend proportionate to Cloudberry. Odal has had a large, restricted cash balance following the return to service programme with SGRE of NOK 179 million proportionate to Cloudberry per third quarter of 2025. The distribution will be funded from Odal’s restricted cash and, upon receipt, will be reclassified from other current assets to cash, increasing Cloudberry’s proportionate cash balance.
Power prices
Cloudberry realized an average net power price of NOK 0.61 per kWh (NOK 0.47 per kWh) compared to the Nordic system price of NOK 0.43 per kWh over the quarter. This showcases Cloudberry’s favorable portfolio composition in the relatively higher price areas compared to the theoretical average of the Nordic region as a whole.
Over the quarter, 10% of Cloudberry’s production was sold at fixed (hedged) prices. As of the reporting date, Cloudberry had established hedges for its power sales in accordance with the table below. Further a pay-as-produced Guarantee of Origin (GO) hedge is in place in the Odin portfolio, covering about 200 GWh over three years at approximately EUR 5 per GO. Cloudberry aims to hedge around 30% of its production to cover all interest and overhead costs, with this strategy being phased in over time.
Hedge total
Asset
Contract (GWh)
Expiry
Type
NO-2
4
2027
Baseload
DK-1
46
2027
Pay as produced
DK-1
39
2026
Baseload
Total
89
Volumes are proportionate to Cloudberry
Asset Management
The Asset Management segment, operated through the fully integrated Captiva Group, delivers comprehensive asset management services and digital solutions, primarily via its associate Kaia (formerly Kraftanmelding). In 2025, several initiatives strengthened the platform: Over the first quarter, Cloudberry integrated Skovgaard Energy’s technically focused asset management team in Denmark adding deep solar and wind expertise. Further, in July the Forte transaction materially expanded the small-scale hydropower portfolio under management establishing a robust base for further hydro growth. In the third quarter, Asset Management continued to prepare to implement in the fourth quarter a new operating model for the Forte hydro assets under which Captiva will assume technical management responsibilities.
Asset Management has further completed the following main activities over the quarter:
Added one additional small hydropower plant, Hellifossen (annual production of 28 GWh), to the framework asset management agreement with Norsk Vannkraft.
Maintained high activity in the markets segment, both internally and for external clients.
Initiated the first phase of a balancing services (aFRR) implementation by prequalifying two turbines in the Odin portfolio, confirmed their technical capability, and established a working group with the balancing responsibility partner (BRP).
Actively managing BRP suppliers in response to changes in balancing fees, operational and contractual models, and operational efficiency, while supporting Cloudberry’s and external client’s participation in new markets.
Optimizing GOs offtake strategies.
Over the third quarter Cloudberry started to realize the impact of the 2025 improvement program within Asset Management initiated after the separation of digital services resulting in a more profitable, focused and efficient organization.
Corporate
In relation to the Forte transaction explained under the Commercial segment Cloudberry repaid approximately NOK 127 million in external debt under its credit facility. New debt has been drawn in Forte Vannkraft of similar amounts.
Cloudberry has an attractive NOK 2.2bn credit facility, with approximately NOK 1.7bn currently utilized. At quarter end, above 70% of total proportionate debt is fixed on long-term contracts at an all-in rate (including margins) below 4% p.a with an average tenure of ~10 years.
Resource rent tax proposal
On 15 October 2025 the Norwegian Government, through the Finance Ministry, presented a consultation proposal to lower threshold for the resource rent tax (grunnrenteskatt) and the natural resource tax (naturressursskatt) on small scale hydropower from 10,000 kVA to 1,500 kVA (approx. from 10 MW to 1.5 MW). If adopted, the proposal would take effect from the 2027 income year.
The Ministry indicates in its proposal that it is considering transitional adjustments for historical investments. The proposing government has a minority position and Cloudberry will engage with all relevant stakeholders to ensure that any potential implementation is as value-neutral as possible for all stakeholders.
Cloudberry is assessing implications for its Norwegian hydropower portfolio. The proposal in its current form will impact Cloudberry’s producing hydropower assets of 178 GWh of estimated net annual production. Herand (47 GWh of estimated net annual production), which is producing asset already subject to resource rent tax regime and will not be affected.
Cloudberry has 31 GWh (estimated net annual production) of small-scale hydro projects under construction not already subject to resource rent tax. The assets, under the current proposal, will be subject to resource rent tax once complete. These projects are currently under review in light of the proposal. Fardalen (38 GWh) and Småvoll (12 GWh) is already under the resource rent tax regime and entitled to a cash compensation for invested capital, and will as such not be affected.
Stable and predictable frameworks are essential to deliver new renewable capacity and long-term value. Cloudberry will engage constructively in the consultation process to mitigate the effects on our portfolio and ensure predictable frameworks. Cloudberry will further evaluate its Norwegian exposure in light of the current unpredictable political landscape.