Third quarter report 2025Cloudberry Clean Energy ASA
Projects and portfolio
Project overview
Since its listing in 2020, Cloudberry has offered investors a unique exposure to a Nordic renewable energy platform supported by an agile and experienced management team. At the time of listing, the Group’s portfolio comprised 15 MW in production and under construction. By the reporting date this has grown to 388 MW. In addition, Cloudberry’s exclusive backlog and permitted projects have increased from 280 MW at listing to 1,613 MW as of the reporting date.
Cloudberry focuses on profitable growth of renewable energy production and storage in attractive price regions while leveraging its local knowledge and network to mature and expand the project portfolio. This strategy has resulted in a diversified and robust cash flow from producing assets across Norway, Sweden, and Denmark, supported by a strong and attractive project pipeline.
While demand for green energy in the Nordics is increasingly sought after - particularly due to the surge in datacenter activity - the market is also becoming more complex and challenging. Cloudberry is perfectly positioned to understand and take advantage of these market dynamics, leveraging its expertise and local presence. Understanding the local dynamics is of increasing importance and Cloudberry is experiencing several interesting incoming dialogues due to its unique positioning.
Note 1: Asset portfolio per reporting date with proportionate ownership to Cloudberry
Portfolio overview per reporting date
Producing assets – proportionate to Cloudberry
Projects portfolio
Cloudberry has a robust and growing backlog and pipeline of new development opportunities across the Nordics. During the third quarter of 2025, Cloudberry reinforced its hydro development capabilities through the Forte transaction, creating a new leading Norwegian hydro player further elaborated in the operational review of the Commercial segment. Combined with Cloudberry’s existing development activities and competence, the new partnership is expected to benefit from increased access to new greenfield hydro projects.
As of the reporting date, Cloudberry has an onshore pipeline of above 2,500 MW across the Nordics and an exclusive backlog of 1,357 MW.
Cloudberry’s focus is towards projects offering favorable economic returns and low environmental impact. We believe these projects will add significant value to Cloudberry, our shareholders and society over time. This is underlined by the reduced availability of renewable projects in the southern parts of the Nordics due to more regulations, a strong focus on nature impact, and local stakeholder interests. Simultaneously, the demand for green power is rising.
Cloudberry collaborates with several large landowners across our geographical footprint, some undisclosed, to secure access to favorable land for development, as well as with established industrial companies as off-takers of green power. This is exemplified by the strategic collaboration with Holmen, one of Sweden’s largest landowners, and the recent partnership with Sveaskog. This approach aims to create beneficial projects for both Cloudberry and the industry.
Cloudberry has organized its development activities through the Projects segment with a focus on three regions:
Norway: Primarily hydro development, and industrial wind & solar projects
Sweden: Primarily wind development and storage/battery
Denmark: Wind and solar development and exploring storage projects
Backlog: Consists of 45 exclusive projects (1,357 MW) across the Nordics: