First quarter report 2026Cloudberry Clean Energy ASA
Operational review
Cloudberry is structured into three collaborative segments: Projects, Commercial, and Asset Management, enabling efficient management and optimization of Cloudberry’s renewable energy assets across the Nordics while supporting growth across all core areas. Please see the 2025 Annual Report for more information about the reporting segments.
Projects
Since listing in 2020, Cloudberry has methodically built a sizeable and diversified development portfolio securing strong partnerships with large landowners across the Nordics. With the portfolio now at scale, the emphasis is shifting from adding new volume to extracting value from what we already control. As part of the refocus in the Project segment, this means directing more time and capital towards projects with shorter lead times and clear routes to construction or monetization including hybrid concepts development initiatives on our producing portfolio. At the same time, we intend to preserve the option value in the longer‑dated backlog and pipeline opportunities but advance these projects in a more phased and selective manner.
Powered land development
Cloudberry is leveraging its Nordic renewable power and infrastructure platform to explore opportunities within data center powered land, a natural extension of the Company’s core business, to leverage the significant demand for data center capacity in the Nordics. With a pan-Nordic footprint and established relationships with local stakeholders and landowners close to key grid infrastructure, Cloudberry is well positioned to identify and secure attractive sites in leading Nordic energy and data center hubs. The Company pursues a capital-light approach focused on securing strategically located, grid-connected land and where access to renewable power is a key differentiator.
Cloudberry has strong in-house capabilities within project development, grid connections, and data center development, complemented by access to data center companies and end-customers. During the quarter, Cloudberry secured its first powered land plot in Norway, attractively located next to a TSO substation and other large data center projects and with an estimated potential of 160 MW (64 MW net to Cloudberry). Cloudberry is further actively assessing additional opportunities across the Nordics with several powered land prospects under consideration and a current pipeline within powered land of approximately 1,000 MW. Over time, this is expected to create an additional value chain adjacent to Cloudberry’s existing development portfolio, with attractive risk-adjusted return potential and clear industrial logic.
Projects under construction
Forte construction projects (Hydro): Through Cloudberry’s 60% ownership in Forte Vannkraft established in the third quarter 2025, Cloudberry is actively involved in the development of several small-scale hydro projects currently under construction. These projects, detailed in the portfolio overview, have a combined estimated annual production net to Cloudberry of approximately 69 GWh, with expected completion dates spanning from third quarter of 2026 to 2028. Over the quarter, there have been some changes to the COD dates due to optimization of drilling schedules with no material estimated economic impact on present value of the projects. The construction projects have overall been progressing as planned over the quarter, with construction cost forecast within the assumptions made in the transaction.
The total estimated remaining capital expenditure (capex) proportionate to Cloudberry for the ongoing hydro construction projects is NOK 340 million, of which NOK 240 million relates to projects subject to resource rent tax under the current regime. As such, approximately NOK 130 million is expected to be reimbursed by the state through cash contributions linked to the current resource rent tax scheme, resulting in a remaining net capex exposure for Cloudberry of NOK 210 million.
Dingelsundet (Battery, SE-3). Hafslund and Cloudberry (50/50 owners) are constructing a 24MW/48 MWh Battery Energy Storage System (BESS) just outside Karlstad with commission expected in the third quarter of 2026. The project continues to progress in line with the execution plan. All groundwork has now been completed, and all main components, including the BESS, have been delivered to site. Initial energization was successfully completed during the first quarter of 2026. The partners also see potential to expand the project with additional battery capacity which may reach ready to build as early as the end of the year.
The project will be financed with an equal split between equity and debt. The total estimated capex is approximately EUR 11 million on a 100% basis or EUR 5.5 million proportionate to Cloudberry. As of the end of the first quarter 2026, the remaining capex for the Dingelsundet project proportionate to Cloudberry amounts to slightly above EUR 2.5 million. Dingelsundet remains fully financed through the previously committed combination of equity and debt. The required equity to fully finance Dingelsundet was injected into the project in 2025. As Dingelsundet is not consolidated in Cloudberry’s financial statements, Cloudberry’s share of the capex can be considered already paid in 2025 in relation to the consolidated cash balance.
Projects with construction permit
There are no material updates on our permitted projects this quarter, and the projects are developing in accordance with plan. Two minor projects were granted permit, one Norwegian solar project and one hydro project with a total estimated annual production of 9 GWh proportionate to Cloudberry which is now included in the asset portfolio table under Other Projects. Please refer to previous quarterly reports for relevant updates about the permitted projects.
Backlog & pipeline
As of the reporting date, the backlog amounts to 1,318 MW across 41 exclusive projects, up from 1,312 MW in the same quarter last year.
During the quarter, the project backlog was reviewed in detail to align prioritization with the updated Projects strategy. As a result, projects totaling 123 MW have been removed from the backlog. Over the same period, new renewable projects of 12 MW, primarily hybridization initiatives adding BESS to existing wind farms, and a 64 MW data‑center powered land project were added. The systematic work to accelerate short‑term value creation while preserving long‑term option value and reduced development expenditures on lower‑priority projects will continue throughout 2026.
Cloudberry is also working on a large non-exclusive pipeline of promising projects across Norway, Sweden, and Denmark, totaling above 2,500 MW of hydro, solar, and onshore wind projects.
Commercial
Commercial’s focus is to increase Cloudberry’s fundamental value by actively engaging in hydro, wind, solar, and storage projects across the Nordic value chain.
Strategic entry into Finland
Cloudberry completed a strategic entry into the Finnish power market in March 2026 through the acquisition of 50% of the 132 MW MLK onshore wind farm. The wind farm has been in full operation since 2022 with an expected annual production of approximately 378 GWh (189 GWh net to Cloudberry). The enterprise value was EUR 75 million, which represents a level below estimated construction cost for a comparable new project. The transaction further diversifies Cloudberry’s Nordic portfolio across geographies and price areas and provides exposure to a market with strong long-term fundamentals, alongside Orrön Energy as industrial partner. There is also a potential upside from a future battery storage solution.
The acquisition was financed through a combination of ring-fenced project debt, new shares in Cloudberry, and cash from the Company’s balance sheet. On completion on 18 March 2026, Cloudberry issued 17,980,314 new shares at a subscription price of NOK 12.4 per share as part settlement of the purchase price. The price per share was based on the current market price, represented by the 20-day volume-weighted average share price prior to signing the share purchase agreement. For further details on the transaction structure and strategic rationale, reference is made to the stock exchange announcements published on 13 and 18 March 2026.
Power production
Cloudberry’s proportionate power production in the quarter totalled 204 GWh, a ~5% increase from 194 GWh in the same quarter last year. The table shows the proportionate production for the quarter, broken down by different price areas.
Production (GWh)
Q1 2026
Q1 2025
Q1 2026 LTM
Q1 2025 LTM
NO-1
39
60
173
154
NO-2
11
16
72
77
NO-3
2
4
19
35
NO-4
-
-
-
3
NO-5
2
6
89
72
SE-3
35
39
129
109
DK-1
102
67
301
241
DK-2
2
2
6
5
FI
10
10
-
Total
204
194
799
695
Of which hydro
13
25
168
179
Of which wind
191
169
632
516
Proportionate wind power production totalled 191 GWh over the quarter (169 GWh).
The increase is driven by strong production from the Danish wind portfolio, which offset weaker wind resources in Norway and Sweden during the quarter and underlines the importance of a diversified portfolio. In addition, the inclusion of the MLK asset in Finland from 18 March contributed positively to the growth. With the exception of the transformer outage at Odal, as described below, there were no other material technical incidents affecting uptime during the quarter.
There has been limited production from hydro in the first quarter of 2026 as expected for the winter season with proportionate hydro power production totalling 13 GWh over the quarter (25 GWh).
Revenue from balancing and flexibility markets
Cloudberry operates in an increasingly volatile power market where value is created through revenue optimization rather than maximizing reported production volumes. Our strategy is to prioritize achieved revenue, which includes curtailing production during periods of negative power prices when it is not economically attractive to produce. This approach may reduce reported production but supports more efficient use of our asset base.
Revenue from balancing and flexibility markets provide an additional contribution on top of spot market revenue, particularly in periods of low prices or high price volatility. Cloudberry is active in the market for downward regulation, where wind production is temporarily reduced when the power system needs less energy. Our Danish wind portfolio, the Finnish asset MLK and the Norwegian asset Odal currently participate in these markets, and we are in the process of including our Swedish wind assets in similar schemes. In addition, MLK has now entered its third flexibility market and can also provide upward regulation when price signals are favorable, and the grid requires more power. Combined, these services create additional revenue opportunities alongside the spot price and support a more resilient earnings profile over time, while contributing to a more stable and efficient power system.
Power prices
Cloudberry realized an average net power price of NOK 1.00 per kWh (NOK 0.71 per kWh) compared to the Nordic system price of NOK 1.03 per kWh over the quarter.
In March, Cloudberry capitalized on gas driven price momentum to hedge 20 MW (est. 50 GWh) of our Danish (DK1) portfolio for 2027. By utilizing a volume-flexible contract priced only slightly below a standard baseload contract that was trading at the time around 85 EUR/MWh, we eliminate the risk of volume shortfalls while obtaining attractive pricing. This strategic structure ensures robust downside protection in low-price scenarios, while our remaining exposure is limited to normal capture rate variations.
Over the quarter, 13% of Cloudberry’s production was sold at fixed (hedged) prices. As of the reporting date, Cloudberry had established hedges for its power sales in accordance with the table below. Further, a pay-as-produced Guarantee of Origin (GO) hedge is in place in the Odin portfolio, covering about 200 GWh until end of 2026 at approximately EUR 5 per GO. Cloudberry aims to hedge around 30% of its production from a risk management perspective, with this strategy being phased in over time.
Power hedge overview
Asset
Contract (GWh)
Expiry
Type
NO-2
4
2027
Baseload
DK-1
46
2027
Pay as produced
DK-1
39
2026
Baseload
DK-11
50
2027
Pay as produced
Total
139
Volumes are proportionate to Cloudberry
1) Volume flex product, no material volume risk. Effective from 01.01.2027
Odal Wind status update
In November 2025, the main transformer serving the Songkjølen area (23 turbines) experienced an outage, resulting in reduced production for this part of the wind farm over the quarter. A replacement spare transformer was installed before Christmas and was successfully energized on 20 January 2026 following completion of testing. Based on current assessment, the repairs of the transformer are in all material respects covered by production warranties and/or insurance. As previously communicated, production at Odal is expected to continue to ramp up through 2026, with availability expected temporarily below long-term normalized levels.
Asset Management
Asset Management delivered improved profitability in the first quarter of 2026 following an efficiency program that has also freed up capacity to create value and capitalize on its expertise for the broader Cloudberry platform. The segment has actively supported key Group initiatives such as hybridization projects, preparations for participation in balancing markets, and technical due diligence for new investments, including the MLK acquisition. Assets under management (AUM) have continued to grow, particularly within BESS and hybrid solutions, and Asset Management has now reached important long-term scale targets of around 1,000 MW total AUM including 1 TWh/100 plants in hydro. The portfolio currently consists of roughly 60% third-party assets and 40% Cloudberry-owned assets, providing both a diversified revenue base and strong industrial synergies.
Other key activities completed during the quarter include:
Signed an agreement to take over technical management of the remaining operational Norwegian plants owned by Locus Energy. The framework agreement now covers 22 plants with a total annual production of ~245 GWh (excluding projects under development and construction)
Added the Smådøla hydropower plant (5 GWh) under the existing asset management framework agreement with Norsk Vannkraft
Completed a successful reorganization of the team following the cost-cutting program
Corporate
Cost cut initiative
In the Q4 2025 report, Cloudberry announced a cost reduction program targeting at least NOK 30 million in annual savings, primarily driven by the refocused strategy within Projects. As part of this strategy, we are shifting resources towards shorter lead‑time opportunities and near‑term value creation, including late‑stage development, value‑enhancing initiatives such as BESS add‑ons to existing assets, and selective brownfield M&A opportunities where we see attractive pricing relative to current capex levels or historical market levels.
In Q1 2026, all planned organizational right‑sizing measures were implemented, resulting in a reduction of more than 20% of the FTEs in the Group. The related savings will be visible in the P&L through 2026 as employment obligations expire. Together with cuts in overhead, actions already executed correspond to annualized savings of approximately NOK 25 million. Following these savings, we are well underway to reach at least the NOK 30 million cost cut that was announced in the Q4 2025 report, which will be achieved through further optimisation of other operational expenditure and a disciplined reduction in devex, in line with our updated Projects strategy. Cloudberry will also continue to evaluate opportunities to simplify its financial reporting, with changes expected to be implemented from the third quarter, the first period not subject to mandatory half‑year reporting requirements.
Corporate debt facility
Cloudberry has an attractive NOK 2.2bn credit facility, with approximately NOK 1.6bn currently utilized. The Company has initiated a refinancing process for this facility, with good progress to date. At quarter end, ~70% of total proportionate debt is fixed on long-term contracts at an all-in rate (including margins) of approximately 4% p.a. with an average tenure of ~9 years.